135MW机组起停过程中的若干问题分析 被引量:1

Analysis of some problems in process of startup and shutdown of 135 MW units
下载PDF
导出
摘要 云浮发电厂3号、4号机组在调试期间和投产后两三年的起、停过程中经常出现振动大的情况,为此,针对起、停过程中存在的若干问题进行了归纳总结,并分析了其原因,最后结合机组的结构特点,从系统改造和运行调整等方面提出了解决措施。 Units 3 and 4 in Yunfu Power Plant often experienced excessive vibration in process of startup and shutdown during commissioning and a couple of years after being put into operation. This paper analyzes some problems in process of startup and shutdown of the units, in light of the structural features of the units, solutions were presented from aspects of system reconstruction and operation regulation, and satisfying results were achieved.
作者 任伟康
机构地区 云浮发电厂
出处 《广东电力》 2006年第4期64-67,共4页 Guangdong Electric Power
关键词 机组振动 胀差 冷却水 汽轮机 vibration of unit differential expansion lug cooling water blocked drain
  • 相关文献

参考文献2

二级参考文献2

  • 1廖天聪.汽轮机原理[M].北京:水利电力出版社,1990..
  • 2朱新华.电厂汽轮机[M].北京:水利电力出版社,1996..

共引文献11

同被引文献6

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部