深埋连拱隧道两种中墙的施工力学行为分析 被引量:7

Behavior of two types of intermediate walls during the excavation of a deep multi-arch tunnel
下载PDF
导出
摘要 采用数值方法,对深埋连拱隧道在Ⅱ、Ⅲ、Ⅳ级围岩条件下整体式直中墙、分离式直中墙的施工受力进行分析,得出了中墙的基本受力规律及中墙施工的关键工序和薄弱部位。结果表明,对于Ⅱ级围岩深埋连拱隧道,两种中墙结构只需构造配筋即可满足要求;而对于Ⅲ、Ⅳ级围岩深埋连拱隧道,则需根据内力配置钢筋。 Adopting numerical method, authors of the paper analyzed the behavior of the single intermediate wall and the separated intermediate walls of a deep multi - arch tunnel when excavated in the rocks of grade Ⅱ ,Ⅲ and Ⅳ respectively. As a result, they found out the crucial construction processes and the weak points for the intermediate walls. As indicated by the analyses, the two types of intermediate walls of a multi - arch tunnel should only be reinforced by construction requirements for rock grade Ⅱ, but should be reinforced according to internal forces for rocks grade Ⅲ and Ⅳ.
出处 《现代隧道技术》 EI 北大核心 2006年第3期1-5,11,共6页 Modern Tunnelling Technology
关键词 深埋连拱隧道 有限元 中墙 施工力学 Deep multi -arch tunnel Finite element Intermediate wall Construction mechanics
  • 相关文献

参考文献6

二级参考文献27

共引文献151

同被引文献50

引证文献7

二级引证文献39

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部