期刊文献+

10kV小水电并网后部分用户电压升高事故分析 被引量:3

Analysis of overvoltage of some consumers after 10 kV grid connected operation of small hydropower stations
下载PDF
导出
摘要 对广东电网广州花都供电局110kV梯面变电站10kV馈线F5故障跳闸的原因进行了详细的分析,认为小水电站并网发电后甩负荷致使用户电压升高是事故的主要原因,为此,从技术和管理两方面提出了具体的整改措施,强调调度中心必须加强对地方小水电的调度管理,制定相应的调度管理制度,才能避免此类事故的发生。 This paper detailedly analyzes an accident of 110 kV Timian Substation under Guangzhou Huadu Power Supply Bureau, in which some power consuming equipments of customers were damaged due to the overvoltage after a 10 kV feeder connected with small hydropower units tripped upon faults. It is concluded that the lack of overvoltage protection for small hydropower generators is the cause of the voltage overshoot. Countermeasures are presented in terms of technology and management. It is stressed that the dispatch center should strengthen the dispatch management of local small hydropower stations and constitute corresponding dispatch management system, so that similar accidents can be avoided.
作者 黎健生
出处 《广东电力》 2006年第6期67-69,共3页 Guangdong Electric Power
关键词 小水电 发电机 甩负荷 事故 small hydropower station generator load shedding accident
  • 相关文献

参考文献4

  • 1DL 400-1991.继电保护和安全自动装置技术规程[S].
  • 2SL/T 179-1996,小型水电站技术改造规程[S].
  • 3GBJ 71-1984,小型水力发电站设计规程[S].
  • 4SL 229-2000,小型水力发电站自动化设计规定[S].

共引文献5

同被引文献13

引证文献3

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部