摘要
滨海核电站的厂址标高是一个涉及海洋水文、气象、海平面变化等多方面因素的技术问题,它除了必须满足核安全导则HAD101/09《滨海核电厂厂址设计基准洪水的确定》的明确规定要求外,还应结合总平面布置与海域工程设计、循环冷却水取排水设计以及厂区土石方工程和核岛厂房基础条件等因素来综合考虑。以广东某核电站工程为例,结合其现场实际条件和工程特点,简要地分析研究滨海核电站厂址标高要考虑的相关问题。
Site elevation of seaside nuclear power stations is a technical problem which involves various factors including ocean hydrology, weather, sea-level variety, etc. It must satisfy the specific requirements of the nuclear safety guide HAD101/09, The Confirmation of Design Basis Flood on Site Elevation of SeasMe Nuclear Power Station. Besides, it should be comprehensively considered in combination with the general layout, sea engineering, cyclic cooling water intake/discharge, site earthwork and the foundation of the nuclear island, etc. Using a nuclear power station project in Guangdong, China as an example, and combined with the site actual conditions and the features of engineering, this paper briefly analyzes relevant factors on site elevation of seaside nuclear power stations.
出处
《广东电力》
2006年第9期30-33,共4页
Guangdong Electric Power
关键词
滨海核电站
设计基准洪水
设计基准标高
厂址标高
seaside nuclear power station
design basis flood
design basis elevation
site elevation