市政工程建设中,人工挖孔桩的施工受到复杂地基及周围环境的影响,通过对实际工程中所遇到的各类影响因素的分析,给出相应的处理方法,以供其他工程参考。
Construction of manual excavated pile affected by complex groundwork and surrounding factors in civic engineering, by analysed different affect factors in actual engineering, give out some disposal means, as a reference to other works.
出处
《山西建筑》
2007年第4期113-114,共2页
Shanxi Architecture
关键词
人工挖孔桩
地下水
流砂
地下管线
manual excavated pile, ground water, quicksand, underground cables