摘要
通过对泵站工程地质、水文情况以及周围建筑物的分析,选择了经济合理的临时施工围堰填筑方案及合理的爆破开挖参数,采用了先进的施工工艺,取得了较好的效益。
By means of analysis on engineering geological condition,hydrological status and situaion of neighour strcture, the economical and reasonable temporary plan to construct cofferdam,the reasonable parameters to blast stone of canal were selected.Due to adopt the advanced construction technique,the better benefit is obtained.
出处
《山西水利科技》
2007年第1期37-39,共3页
Shanxi Hydrotechnics
关键词
和信电厂
泵站进水渠
控制爆破
设计施工
Hexin Power Station intake canal of pumping station controlled blasting design and construction