期刊文献+

支井河大桥C20大体积混凝土冬季温控施工研究 被引量:14

Research on the Temperature Control Measure in the Winter Construction of C20 Large Volume Concrete of Zhijing River Bridge
下载PDF
导出
摘要 通过分析大体积混凝土温度裂缝产生机理,提出了大体积混凝土施工温度控制的措施,并针对支井河大桥C20大体积混凝土冬季施工的特点,通过选择合适的原材料、优化混凝土配合比设计,对混凝土在无保温措施和采取外部保温措施2种情况下的内外温差进行比较分析,最终确定选择外部保温的温控措施,并成功地进行了C20大体积混凝土的浇筑。 This paper analyzed the mechanism about temperature cracks of large volume concrete, and put forward the content about temperature control of Large Volume Concrete Construction. Based on the status of C20 large volume concrete of Zhijing River Bridge in the winter construction, it is concluded that large volume concrete cracks could be controlled. By the select of raw materials, the design of mixture ration and analyzing no surface temperature preservation and surface temperature preservation on the concrete, the surface temperature preservation was fixed, At last the C20 large volume concrete was successfully applied.
出处 《武汉理工大学学报》 EI CAS CSCD 北大核心 2007年第3期111-113,共3页 Journal of Wuhan University of Technology
关键词 大体积混凝土 外保法 温度裂缝 温度控制 large volume concrete surface temperature preservation temperature cracks temperature control
  • 相关文献

参考文献4

  • 1叶琳昌,沈义.大体积混凝土[M].北京:中国建筑工业出版社,1987.
  • 2GB50204-92,混凝土结构工程施工及验收规范[S].辽宁:辽宁科技出版社,1992.35.
  • 3埃克特ERG.传热与传质分析[M].北京:科学出版社,1986..
  • 4韩振兴.热工基础[M].北京:航空工业出版社,1991.

共引文献8

同被引文献37

引证文献14

二级引证文献122

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部