摘要
介绍了金隆公司目前正在进行的挖潜改造工程方案规模选择的依据、需要改造设备内容和改造思路、工程计划进度等,认为本次挖潜改造最适宜的规模为350 kt/a矿产粗铜、400 kt/a阴极铜;工程计划分步实施,在2008年全部建成投产。
The expansion project in J inlong Copper, mainly from the aspect of plan, guideline, equipments and schedule etc, are introduced and analyzed. The suitable size of this project is 350 kt blister per year and 400 kt cathode copper per year after this analysis. This project will operate as schedule, and will completed in 2008.
出处
《有色金属(冶炼部分)》
CAS
北大核心
2007年第2期29-32,共4页
Nonferrous Metals(Extractive Metallurgy)
关键词
闪速熔炼
挖潜改造
产能规模
Flash Smelting
Expansion project
Production capacity