摘要
介绍了山东电力超高压公司自2003年以来500kV输电线路由于风偏造成的跳闸故障,对造成故障的原因进行了力学分析,并提出了防止风偏故障的措施。
This thesis has enumerated some breakdown faults of 500KV transmission lines because of wind leaning since 2003 in Shandong Extrahigh Power Company, carried on mechanics analysis for the reasons of faults, and proposed the preventing methods.
出处
《山东电力技术》
2007年第2期69-71,共3页
Shandong Electric Power
关键词
风偏故障
原因分析
防范措施
wind leaning fault
analyzing reason
preventing methods