摘要
针对洋山深水港区一期港内水域疏浚工程码头桩区疏浚时遇到的问题进行研究,采用吹泥船排水口加装弯头,形成高压水冲力的施工工艺,使得码头桩区边坡最终达到了设计的要求。
Problems encountered during the dredging operations in the piled areas in Phase I of Yangshan Deep Water Port were studied. As a result, an elbow pipe was installed at the discharge end of the dredger to create a high-pressure jet force to help dredging. With this method, the shore slope in the piled areas for the wharfs in the port was finally dredged to the design requirements.
出处
《中国港湾建设》
北大核心
2007年第3期55-57,共3页
China Harbour Engineering
关键词
码头桩区
疏浚
水冲力
piled area for wharfs
dredging
jet force