景洪水电站右岸下游引航道临时围堰施工变更索赔 被引量:3

Change claim on construction of temporary cofferdam for downstream leading channel of Jinghong Hydropower Station
下载PDF
导出
摘要 工程索赔是一项知识和技术面很广,复杂而又系统性很强的工作,文中通过分析景洪水电站下游引航道围堰变更索赔过程,说明施工单位如何根据实际施工条件和投标时施工条件的改变,提出变更立项申请,实现变更报价审批的过程,同时在人才资源的管理和利用上提出一些见解。 Through the analysis on the process of change claim on construction of temporary cofferdam for the downstream leading channel of Jinghong Hydropower Station, the full process of how to make the application for change of construction project based on the change between the actual construction condition and the construction condition during bidding and how to realize the approval of the quotation of contract change is described herein for the construction enterprise, and then some viewpoints on the management and utilization of the relevant talent resources are put forward as well.
作者 黄丹 柳芳
出处 《水利水电技术》 CSCD 北大核心 2007年第7期19-21,共3页 Water Resources and Hydropower Engineering
关键词 景洪水电站 下游引航道 围堰 施工变更 变更索赔 Jinghong Hydropower Station downstream leading channel cofferdam change of construction project change claim
  • 相关文献

同被引文献9

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部