洞巴水电站溢洪道溢流堰的混凝土浇筑使用轻型桁架模板。在浇筑溢洪道溢流堰不规则圆弧段混凝土施工中,提出质量缺陷的补救对策,以供同行参考。
The concrete placement for spillway and overflow weir at Dongba Hydropower Station employs light truss type formwork.Some remedies to quality defects during the concrete placement at irregular circular arc segment of spillway and overflow weir are proposed and may be referred to by similar projects.