基于机动时间的项目工期单因素不确定性分析 被引量:4

Single-factor uncertainty analysis of project's duration based on float
下载PDF
导出
摘要 为了分析单个工序结束时间的变化对项目工期的敏感性,以总时差的概念及定理为基础,利用概率分析的原理及方法,确定了工序结束时间的变化在不同条件下的概率值,构建了项目工期单因素不确定性分析的指标评价体系,简要说明了指标体系中确定相关参数的思路与方法;然后,采用单因素敏感性分析法,重点分析了关键工序结束时间的变化对项目工期的敏感性,给出了不同关键工序结束时间的变化对项目工期的敏感性的判别方法,以及如何从被考虑的多个关键工序中找出需要重点考虑的对总工期敏感性最强的工序;最后,通过算例进行验证和说明.该评价体系在实践中有助于项目进度计划与控制,重点监督与控制对总工期敏感性强的工序,为项目工期的多因素不确定性分析奠定理论基础. In order to analyze the sensitivity of variety of single activity completion time to project's duration, by probabilistic analysis principle and approach, the probability of terminative time's change of activity under different conditions was confirmed, and the system of decision evaluation index was designed which contains the method of confirming correlative parameters in the system on the basis of total float theorem. The sensitivity of variety of critical activity's completion time to project's duration was analyzed with the analysis tech- nique of single-factor sensitivity, and how to select critical activities which are the most sensitive to total time limit from all activities considered. Finally the process was validated and illuminated by illustrating. The system is helpful to supervise and control the sensitive activity to project duration, and contribute to project scheduling and planning, which establishs theoretic foundation for analyzing multi-factor uncertainty problem of project's duration.
出处 《北京航空航天大学学报》 EI CAS CSCD 北大核心 2007年第12期1466-1470,共5页 Journal of Beijing University of Aeronautics and Astronautics
基金 国家自然科学基金资助项目(70671040) 国家教育部博士学科点科研基金资助项目(20050079008)
关键词 图解评审法 关键路线法 敏感性分析 评价指标 program evaluation and review technique critical patch method sensitivity analysis evaluation index
  • 相关文献

参考文献9

  • 1Elmaghraby S E. On criticality and sensitivity in activity networks [ J]. European Journal of Operational Research, 2000, 127 : 220 - 238.
  • 2Dodin B M, Ehnaghraby S E. Approximating the criticality indices of the activities in PERT networks [ J ]. Management Science, 1985, 31:207-223.
  • 3Kulkarni V G, Adlakha V G. Markov and Markov-regenerative pert networks [ J ]. Operations Research, 1986, 34 : 769 - 781.
  • 4Bowman R A, Muckstadt J A. Stochastic analysis of cyclic schedules [ J ]. Operations Research, 1993, 41 : 947 - 958.
  • 5Sigal C E, Pritsker A B, Solberg J. Use of eutsts in Monte Carlo analysis of stochastic networks [ J ]. Mathematics and Computers in Simulation, 1979, 21 : 376 -384.
  • 6Bowman R A. Efficient estimation of arc criticalities in stochastic activity networks [J]. Management Science, 1995, 41 : 58 - 67.
  • 7Williams T M. Criticality in stochastic networks [ J ]. Operations Research, 1992, 43 : 353 - 357.
  • 8Cho J G, Yum B J. An uncertainty importance measure of activities in PERT networks [ J]. International Journal of Production Research, 1997, 35 : 2737 - 2770.
  • 9李星梅,乞建勋,牛东晓.三个平行序链的顺序优化决策[J].中国管理科学,2006,14(4):69-74. 被引量:5

二级参考文献15

  • 1乞建勋 王文庆.三元序链的优化理论[J].系统工程理论与实践,1991,(3).
  • 2唐国春,张峰,罗守承等.现代排序论[M].上海:上海科学普及出版社,2002.185-189.
  • 3乞建勋,关金锋.二行N元链格的优化方法[C].全国运筹学应用交流与研讨会论文集,1994.
  • 4Talel Ladhari,Mohamed Haouan.A computational study of the permutation flow shop problem based on s tight lower bound[J].Computers & Operations Research,2005,32:1831-1847.
  • 5Fouad Riane,Abdelhakim Artiba,Salah E.Elmaghraby.A hybrid three-stage flowshop problem:Efficient heuristics to minimize makespan[J].European Journal of Operational Research,1998,109:321-329.
  • 6Jose M.Framinan,Rainer Leisten,Rafael Ruiz-Usano.Comparison of heuristics for flowtime minimization in permutation flowshops[J].Computers & Operations Research,2005,32:1237-1254.
  • 7Chinyao Low.Simulated annealing heuristic for flow shop scheduling problems with unrelated parallel machines[J].Computers & Operations Research,2005,32:2013 -2025.
  • 8Jozef Grabowski,Jaroslaw Pempera.Some local search algorithm for no-wait flow-shop problem with makespan criterion[J].Computers & Operations Research,2005,32:2197-2212.
  • 9Irene N.Lushchakova,Svetlana A.Kravchenko.Twomachine shop scheduling with zero and unit processing times[J].European Journal of Operational Research,1998,107:378-388.
  • 10George Kyparisis,Christos Koulamas.Flow shop and open shop scheduling with a critical machine and two operations per job[J].European Journal of Operational Research,2000,127:120-125.

共引文献4

同被引文献46

引证文献4

二级引证文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部