为适应日益增长的经济和交通发展需求,修建以4车道公路隧道为代表的超大断面低扁平率公路隧洞的需求初露端倪,这类隧道的低扁平率特征使传统的隧道支护体系面临许多困难,急待开发新型的隧洞支护体系。采用FLAC数值模拟平台研究了基于隧洞"先成结构法"支护理念的"先成预应力结构"新型支护体系在提高超大断面低扁平率公路隧洞洞室稳定性方面的效果,为"先成结构法"支护理念在超大断面低扁平率公路隧洞中的应用实施提供了有力的支持。
To satisfy the rapid development of economy and traffic, super cross-section highway tunnel with lower flat-ratio such as four-lane tunnel seems very necessary; and its lower flat-ratio makes that the traditional tunnel support system is difficult to support it. New support system has to be researched to enhance present status, The effects of an innovative "pre-built and prestressed" support system that come of "pre-built" ideology in enhancing the stability of super cross-section highway tunnel with lower flat-ratio have been studied by numerical modeling with FLAC, which are significant for the practice of "pre-built" ideology in super cross-section highway tunnel with lower flat-ratio.
出处
《岩土力学》
EI
CAS
CSCD
北大核心
2008年第1期240-244,共5页
Rock and Soil Mechanics
关键词
超大断面
低扁平率
公路隧洞
洞室稳定性
支护体系
先成预应力结构
数值分析
super cross-section
lower flat-ratio
highway tunnel
tunnel stability
support system
pre-built and prestressed support system