摘要
采用网络计划技术对导弹测试流程进行进度控制,得到工序流程的时间信息。建立网络图的数据结构,如邻接矩阵、结构矩阵等,通过计算机仿真的方法模拟测试工序的时间进度,并用横道图的形式描绘出测试过程,较容易地发现测试设备的约束情况,通过增加一定数量的测试设备,对提高导弹测试速度具有一定的帮助。
Network planning was adopted for schedule control of the missile testing process and the time information,of the process was acquired. Data structures of the network chart such as adjacency matrix and construction matrix were built, the schedule of the test process was simulated, the test process was shown by diagram, and then constraint of the test equipment can be known easily. Increasing the quantity of Test equipment is helpful for missile test speed improvement.
出处
《弹箭与制导学报》
CSCD
北大核心
2008年第1期39-42,共4页
Journal of Projectiles,Rockets,Missiles and Guidance
关键词
邻接矩阵
网络计划
批量测试
网络图
adjacency matrix
network planning
batch testing
network chart