摘要
神东矿区使用的ACE带式输送机张紧系统的APW绞车,在使用过程中多次出现故障。针对出现的故障,进行了详细分析和技术改造,增加了张紧缓冲装置。改造后的带式输送机张紧缓冲装置使用效果良好。
The APW winch of ACE belt conveyor tensioning system is used in Shendong Coal Mine, and there are always some troubles on it. After detailed research, the tensioning buffer system is added to it, and it is used very well after this innovation.
出处
《煤矿机械》
北大核心
2008年第7期136-137,共2页
Coal Mine Machinery
关键词
ACE带式输送机
张紧
技术改造
ACE belt conveyor
tensioning
technical innovation