摘要
通过对综放工作面采煤机、刮板输送机和液压支架的合理配套,确定了巷道和切眼的尺寸,实现了工作面月产1.0Mt高产高效的要求,为今后国内高产高效工作面设备配套与巷道、切眼尺寸的确定提供借鉴。
Dimensions of roadway and open-off cut were confirmed with reasonable equipment coordination of coal cutter, scraper and hydraulic supports in full-mechanized caving mining face. High production of 1.0 Mt and high effect of mining face were realized, which provided reference for equipment coordination of mining face with high production and high effect and dimension confirmation of open-off cut.
出处
《煤矿开采》
2008年第3期67-68,共2页
Coal Mining Technology
关键词
设备配套
巷道
切眼
equipment coordination
roadway
open-off cut