期刊文献+

顶管施工引起地面沉降分析和计算 被引量:17

Research on Ground Deformation Caused by Pipe Jacking Construction
下载PDF
导出
摘要 预测和控制顶管施工引起的土层变形是城市环境土工学的一个重要研究课题。采用理论与经验相结合的方法,考虑施工应力引起的土体位移,对顶管施工引起地面横向沉降的经典理论方法Peck地面沉降槽理论公式进行了修正,使之更加符合工程实际。并通过工程实例进行了验证。 The prediction and control of ground deformation have become one of the main research subjects.In this dissertation,according to the basic theories and the experiences,a strict research was carried on soft body's dis- placement caused by construction stress.Peck's formula of ground deformation trough theory was amended to more fit realities of the projects.This method has been tested by practice of some projects.
作者 詹红梅
出处 《地下空间与工程学报》 CSCD 2008年第3期583-585,共3页 Chinese Journal of Underground Space and Engineering
关键词 顶管施工 正面推力 地层损失 地面沉降 soft mechanics pipe-jacking stratum loss ground settlement
  • 相关文献

参考文献2

  • 1Peck, R. B. Deep excavations and tunneling in soft ground[C]. 7^th International Conference on Soil Mechanics and foundation Engineering, State - of - the - Art, Volume, Mexico City : 225 - 290.
  • 2B.A.弗洛林.土力学原理(第一卷)[M].同济大学土力学与基础教研室译.中国工业出版,1965:109-112.

同被引文献98

引证文献17

二级引证文献56