基于机会约束规划的ERP实施方案优化模型 被引量:2

Optimization Models of ERP Implementation Project Based on Chance-Constrained Programming
下载PDF
导出
摘要 为了解决企业ERP实施规划方案中的时间、成本、质量不确定优化问题,结合PERT技术提出了基于机会约束规划的实施进度、实施进度-费用和实施质量优化模型及进度-费用-质量联合折衷模型.采用随机模拟技术通过Monte Carlo仿真给出了项目实施风险的概率估计,并利用嵌入PERT的基于随机模拟的遗传算法对模型进行求解.最后通过算例验证了文中提出的模型的合理性和算法的有效性,为企业ERP实施方案的规划提供了可靠的方法. In order to solve the uncertain optimization problems of time, cost and quality existing in the project implementation process of enterprise resource planning (ERP), the program evaluation and review technique (PERT) is employed to establish the optimization models of the implementation schedule, the implementation schedule-cost tradeoff, the implementation quality and the implementation schedule-cost-quality tradeoff. Then, the risk probability of project implementation is estimated via the Monte Carlo simulation. Moreover, a PERT-embedded genetic algorithm based on the stochastic simulation technique is introduced to solve the proposed models. It is demonstrated by an example that the proposed models and algorithm are reasonable and effective, and are reliable for the programming of ERP project implementation.
出处 《华南理工大学学报(自然科学版)》 EI CAS CSCD 北大核心 2008年第9期64-70,共7页 Journal of South China University of Technology(Natural Science Edition)
基金 国家"863"/CIMS主题资助项目(2003AA413210)
关键词 项目管理 企业资源计划 机会约束规划 计划评审技术 遗传算法 project management enterprise resource planning chance-constrained programming program evaluation and review technique genetic algorithm
  • 相关文献

参考文献9

二级参考文献29

  • 1张国庆.ERP实战策略(之五)——实施过程中的项目管理[J].信息系统工程,2003,16(4):63-63. 被引量:2
  • 2丁丁.聚焦ERP的中国道路[J].电脑知识与技术(技术论坛),2005(2):68-69. 被引量:4
  • 3SHOUMAN M A,El-NOUR A,EBRAHIM S,et al.Mixed integer linear programming model for a time cost trade-off[J].Advances in Modelling & Simulation,1991,22(4):53-63.
  • 4ERENGUC S,SELCUK T.Time/cost trade-off problems with discounted cash flows using generalized benders decomposition[J].Naval Research Logistics,1993,40(1):25-50.
  • 5FENG Chungwei,LIU Liang,BURNS S A.Stochastic construction time-cost trade-off analysis[J].Journal of Computing in Civil Engineering,2000,14(2):117-126.
  • 6ICMELI O,ERENGUC S S.Resource constrained time/cost tradeoff project scheduling problem with discounted cash flows[J].Journal of Operations Management,1996,14(3):255-275.
  • 7HECHT M,HANDAL J.A discrete-event simulator for predicting outage time and costs as a function of maintenance resources[A].Proceedings of the Annual Reliability and Maintainability Symposium[C].2002,612-617.
  • 8BABU A J G,SURESH N.Project management with time,cost and quality considerations[J].European Journal of Operational Research,1996,88(2):320-327.
  • 9KHANG D B,MYINT Y M.Time,cost and quality trade-off in project management:A case study[J].International Journal of Project Management,1999,17(4):249-256.
  • 10McKim R, Hegazy T, Attalla M. Project performance control in reconstruction projects[J]. Journal of Construction Engineering and Management, 2000, 126 (2): 137-141.

共引文献192

同被引文献17

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部