邯郸市东污水处理厂再生水回用工程总设计处理规模为5万m3/d,其中一期工程规模为3万m3/d。该工程以东污水处理厂二级出水为原水,采用"高密度沉淀池+V型滤池"处理工艺。介绍了工程的设计与运行情况,着重介绍了高密度沉淀池的设计参数与构造。运行结果表明,工艺运行情况稳定,出水水质达到设计要求,主要回用于城市杂用水及景观环境用水,部分回用于工业用水。
The total processing scale of the reclaimed water reuse project of Handan East Wastewater Treatment Plant is 5× 10^4 m^3/d and the first-stage project of it is 3 × 10^4 m^3/d. The raw water source of this project is the further treated wastewater of the Handan East Wastewater Treatment Plant and the combination of high density settling tank and V-filtration process is employed in this project. This paper introduced the design and operation of this project, especially the designing parameters and construction of the high density settling tank. The operation results showed that the quality of treated water of this project satisfied the design requirement. Most part of the treated water is used as urban misellaneous water and scenic water, part of it is used as industrial water.
出处
《给水排水》
CSCD
北大核心
2009年第1期31-34,共4页
Water & Wastewater Engineering
关键词
污水处理厂
再生水
回用
工艺设计
水质
Wastewater treatment plant
Reclaimed water
Reuse
Process design
Water quality