摘要 针对环氧沥青混凝土桥面铺装对施工过程中时间、温度、水分控制要求苛刻、施工质量要求高的特点,结合武汉阳逻大桥钢箱梁悬索桥桥面环氧沥青铺装施工的成功经验,总结了环氧沥青混凝土铺装粘结层备料、喷洒和环氧沥青混合料拌合、运输、摊铺、碾压、接缝处理和养护施工工艺,并研究施工过程可能会出现的天气突变、施工机械故障、混合料温度变化等突发情况,提出环氧沥青铺装施工应急预案。 Epoxy asphalt concrete bridge pavement has strict requirements on time, temperature and moisture during construction, as well as construction quality. Based on the successful construction experience of Wuhan Yangluo Bridge, the construction technologies of epoxy asphalt concrete pavement for suspension bridge are introduced. Key construction technologies are summed up, including preparation and spraying of bonding materials, mixing, transporting, extending of epoxy asphalt concrete as well as joint treatment and curing. The emergency response plan is proposed by researching the emergencies during construction, such as weather fluctuation, equipments failure and change of mixture temperature etc.
出处 《施工技术》 CAS 北大核心 2009年第1期24-26,共3页 Construction Technology
关键词 桥梁 桥面铺装 环氧沥青混凝土 施工工艺 应急预案 质量控制 bridge bridge pavement epoxy asphalt concrete construction technology emergency response plan quality control
  • 相关文献

参考文献5

  • 1东南大学,武汉绕城公路建设指挥部.武汉阳逻长江公路大桥钢桥面铺装技术研究报告[R].南京,2007.
  • 2Luo Sang, Wang Jianwei, Qian Zhendong. Research on the performance of locally developed epoxy asphalt mixes [AI// Proceedings of the 26th southern african transport conference (SATC 2007) [C]. Pretoria: 2007, 736-744.
  • 3Qian Zhendong, Luo Sang, Wang Jianwei. laboratory evaluation of epoxy resin modified asphalt mixtures [ J ~. Journal of Southeast University (English Edition), 2007, 23(1) : 117-121.
  • 4张磊,唐小平,李洪涛.大跨径钢桥面粘结层材料和施工技术研究[J].中南公路工程,2005,30(4):162-166. 被引量:8
  • 5胥志宏,付斌,李玉龙,牟建波.东海大桥桥面防水层及浇注式沥青混凝土铺装施工[J].上海公路,2005(2):21-24. 被引量:2

二级参考文献8

  • 1[3]BeratunssellefürGu?asphaltanwendunge. V. asphaltkalender 2001.
  • 2[4]Der bundesminister für verkehr. Technische preüfvorschriften für die prüfung der dichtungsschichten und derabdichtungs-Systeme für brükenbel?gen aufstahl TP-BEL-ST.
  • 3[5]Derbundesministerfürverkehr. Technische Lieferbedingungen für Baustoffe der dichtungsschichten für brükenbel?gen aufstahl TP-BEL-ST.
  • 4黄卫.南京长江第二大桥钢桥面环氧混凝土铺装技术及应用[R].,2000..
  • 5Charles Seim. Inspection of the surfacing of the steel deck of the RAMA IX Bridge[R].19SS.6.
  • 6黄卫.润扬长江公路大桥钢桥面铺装材料试验研究阶段报告[R].东南大学交通学院,2002..
  • 7黄卫,李淞泉.南京长江第二大桥钢桥面铺装技术研究[J].公路,2001,46(1):37-41. 被引量:65
  • 8胡光伟,黄卫,张晓春.润扬大桥钢桥面铺装层力学分析[J].公路交通科技,2002,19(4):1-3. 被引量:39

共引文献8

同被引文献101

引证文献12

二级引证文献69

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部