摘要
结合龙华口水电站坝址区水文、地质条件,通过现场高喷试验,确定了高喷参数,阐述了施工导流围堰高喷防渗墙施工过程中质量控制要点及所采取的措施。
Connecting with the hydro-geological conditions of the dam site of Longhuakou Hydropower Station, and through the field high-pressure jet-grouting test, this paper determines the parameters of the high-pressure jet-grouting, and expounds the main points of the quality control in the construction of high-pressure jet-grouting watertight wall of the construction diversion cofferdam and adopted measures.
出处
《科技情报开发与经济》
2009年第3期209-211,共3页
Sci-Tech Information Development & Economy
关键词
施工导流围堰
高喷防渗墙
质量控制
龙华口水电站
construction diversion cofferdam
high-pressure jet-grouting watertight wall
quality control
Longhuakou Hydropower Station