摘要
针对隧道洞口浅埋偏压段的施工,从理论及施工过程中所采取的措施出发,对可能发生的状况提出具体的处理方法。实践证明,所采取的措施及处理方法保证了隧道洞口的施工安全及施工进度。
Aiming at the construction of shallowly-buried bias part of tunnel adit, specific treating approaches are presented for possible situations based on theory and measure applied during construction. The practice shows that the measure and treating approaches ensure the safety and progress of construction of tunnel adit.
出处
《筑路机械与施工机械化》
北大核心
2009年第4期73-75,共3页
Road Machinery & Construction Mechanization
关键词
浅埋
偏压
施工技术
加固措施
shallowly-buried
bias
construction technology
reinforcement measure