基于Petri网的施工进度建模及优化方法 被引量:8

Study on the Construction Modeling Based on Network Plan
下载PDF
导出
摘要 构建并定义了基于时间Petri网的分级施工网络计划模型,定义了分级库所与任务变迁。在此基础上,对进度计划优化进行了研究。根据我国工程项目管理模式,为满足建筑施工进度计划优化需求,基于HNPC模型建立了一个二级网络计划优化模型;对资源约束工期优化进行了研究,给出了一种遗传算法的解决策略;以Petri网模型的变迁激发序列作为染色体进行计算,使算法和Petri网模型统一起来,并通过实例证明了采用本方法的有效性。 Based on the hierarchical network plan and the Petri net, the construction process model is constructed. The hierarchical network plan of construction based on the time petri net, hierarchical place and task transition are defined, the correctness of above two models is analyzed based on the accessibility of Petri net. The method of schedule plan optimization is studied. According to the management of construction project in our country, the two--level network optimization model is established based on the HNPC model to satisfy the optimistic demands. The construction schedule optimization under resource constraints is researched, a solution strategy based on genetic algorithm is presented. The excited sequence of transition is traded as population to be calculated, the Petri Net model and the algorithm are integrated. Finally, a case study is carried out to prove the validity of this method.
出处 《系统管理学报》 北大核心 2009年第2期193-198,共6页 Journal of Systems & Management
基金 黑龙江省科技厅资助项目(GA05A101)
关键词 施工建模 赋时PETRI网 资源约束 construction modeling timed Petri net resource-constrained
  • 相关文献

参考文献10

二级参考文献30

  • 1邬晓光.桥梁施工网络计划限定资源时优化研究[J].西安公路交通大学学报,1997,17(1):31-34. 被引量:6
  • 2康凤举.现代仿真技术与应用[M].北京:国防工业出版社,1998..
  • 3Bowden F D J. A Brief Survey and Synthesis of the Roles of Time in Petri Nets[J]. Mathematical and Computer Modeling, 2000, 31: 55-68.
  • 4William G. Bulgren. Discrete system simulation[M]. Prentice-Hall, Inc, Englewood Cliffs, 1982.
  • 5Wakefield Ron R. Petri Nets for simulation and modeling of construction systems[J]. Journal of Construction Engineering and Management, 1997, 123(1): 105-112.
  • 6Peterson James L. Petri net theory and the modeling of systems[M]. Prentice-Hall, Inc, Englewood Ciffs, 1981.
  • 7Chan W T, David K H Chua, Govindom Kannan. Construction Resource Scheduling with Genetic Algo\rithms[J].Journal of Construction Engineering and Management,1996,(6):126-132.
  • 8Herrera Fetal.A Model of Consensus in Group Decision Making under Linguistic Assessments[J]. F S S, 1996,(78):73-87.
  • 9Glodberg D E. Optimization and Machine Learning[M]. Publishing Company Inc, 1989.25-28.
  • 10江景波.网络计划技术[M].北京:冶金工业出版社,1988..

共引文献39

同被引文献87

引证文献8

二级引证文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部