摘要
通过某高速现浇预应力连续箱梁工程,详细介绍了该项目的地基处理、搭设支架、支架预压、支立模板、钢筋工程、混凝土工程、梁体预应力体系施工、支架拆除等施工工艺。为今后类似工程的处理,从施工方面提供了一定的借鉴。
Through cast-in-place pre-stressed concrete continuous box girder project, the construction processes such as ground treatment, scaffold erection, scaffold pre-compression, template erection, steel project, concrete project, girder pre-stressed system construction, scaffold backout, etc of this project were introduced in detail. A reference was provided from the aspect of construction for the treatment of similar project of the future.
出处
《工程建设与设计》
2010年第1期119-123,共5页
Construction & Design for Engineering
关键词
现浇预应力混凝土
连续箱梁
施工技术
cast-in-place pre-stressed concrete
continuous box girder