摘要 黄河积石峡水电站由于条件限制,压力钢管底部和某些重点部位的入仓混凝土无法振捣,要求采用高流态自密实混凝土,为此进行了高流态混凝土配合比的试验研究。通过对原材料(水泥、粉煤灰、外加剂、骨料)试验、混凝土配合比(粗骨料比例、砂率、减水剂对水泥的适应性、减水剂对混凝土的扩散度损失的影响、混凝土配合比)试验、试验结果(混凝土拌和物性能、混凝土力学性能、混凝土耐久性指标)校核等。得到积石峡水电站工程施工要求的高流态自密实混凝土经济配合比。实际应用表明,浇注的上万方高流态、自密实的混凝土,未发现裂缝现象,保证了工程主节点的工期,取得了良好的技术性能和经济效益。 Because of the limit of conditions,the high guss and self-compacting concrete should be used in the construction for some key positions of Jishixia Hydropower Station.Therefore,the tests and researches are made for this kind of concrete,including the tests for the raw materials,the tests for mix propotions,the check and proof for the test results and so on,so as to obtain the economic mix propotion of the concrete in the construction of the project.The results show that by using this kind of concrete,no cracks appear in the concreting bodies,so as to ensure the time limit of the main nodal points of the project,and achieve well technical characteristics and economic benefits.
出处 《水利与建筑工程学报》 2010年第1期42-45,共4页 Journal of Water Resources and Architectural Engineering
关键词 高流态混凝土 配合比 应用研究 high guss concrete mix proportion application research
  • 相关文献

参考文献6

  • 1张龙,郭林涛,洪镝.水利水电工程试验数据分析计算方法[M].北京:中国水利水电出版社和知识产权出版社,2009.
  • 2DL/T5330-2005.水工混凝土配合比设计规程[s].北京:中国电力出版社,2006.
  • 3许建民.混凝土施工裂缝与控制[J].水利与建筑工程学报,2008,6(4):90-91. 被引量:11
  • 4SL352-2006.水工混凝土试验规程[s].北京:中国水利水电出版社,2007.
  • 5DL/T5144-2001水工混凝土施工规范[S].北京:中国电力出版社,2002.
  • 6JGJ55-2000普通混凝土配合比设计规程[S].北京:中国建材工业出版社,2001.