摘要
随着科学技术和社会经济的发展以及自然条件的变迁,初步设计制订的三峡水库运行方式已经不能适应要求。为此,分析比较了7种来水条件在不同蓄水方式下的三峡电站电量,综合考虑防洪、航运、电网运行等要求,提出目前可行的优化设计方案。今后可在此基础上继续深入全面研究,进一步提前蓄水开始时间和加快蓄水进度。
With the technical and socio-economic development and the changes in natural conditions,the operational scheme of Three Gorges Reservoir decided by preliminary design has been unable to meet demand.After taking into account the deman ds for flood control,navigation,power grid operation and others,the power generations under different impounding scheme with 7 runoff conditions are analyzed,and the optimization on water storage scheme are presented.On this basis,the start impounding time and water storage program can be study comprehensively in the future.
出处
《水力发电》
北大核心
2009年第12期61-63,共3页
Water Power
关键词
蓄水方式
优化设计
三峡水库
storage scheme
design optimization
Three Gorges Reservoir