斜井施工装运系统模拟技术研究 被引量:4

Transportation System Simulation Technology of Slope Mine Construction
下载PDF
导出
摘要 文章分析了斜井施工存在的问题和影响斜井施工的主要因素,重点对斜井装运系统进行了系统分析和系统划分,在此基础上,通过大量的调研,建立了斜井施工装运系统的计算机模拟模型,用vb语言编制了模拟程序,就模拟参数的数学模型做了详尽的介绍,就一套单钩、一套双钩、两套单钩三种不同的提升方式进行了演示试验,通过模拟结果的分析,可以清楚地发现系统存在的问题,从而达到预测、优化的目的。实践证明装运系统的计算机模拟技术对斜井施工的科学设计、科学选型、科学管理具有积极的推动作用和重要的现实意义。 This paper analyzes the problems of slope mine construction and the main factors affecting slope mine construction, with emphasis on the transportation system of slope mine construction in system analysis and system division, on this basis, a computer simulation model of through a lot of research, transportation system for slope mine construction was established, using VB language to compile a computer simulation program, the simulation parameters of the mathematical model were introduced in detail, on a set of single-hook, a double hook, two sets of single-hook in three different ways to enhance the demonstration test, through the simulation results of the analysis, it is clear to find the system problems to achieve the prediction, optimization purposes. Practice shows that the transportation system computer simulation of the slope mine construction has a positive role in promoting of and important practical significance for scientific design and scientific selection, scientific management.
出处 《地下空间与工程学报》 CSCD 北大核心 2010年第2期348-353,368,共7页 Chinese Journal of Underground Space and Engineering
基金 山西省科学技术发展计划项目(20080321068)
关键词 斜井施工 装运系统 计算机模拟 优化设计 slope mine construction transportation system computer simulation optimization design
  • 相关文献

参考文献10

二级参考文献12

共引文献24

同被引文献12

引证文献4

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部