多项目选择计划及其两层决策免疫遗传算法 被引量:5

Multi-project selective planning and its immune genetic algorithm for bi-level decision
下载PDF
导出
摘要 探讨项目计划管理中,资源受限下含承继约束的多项目选择计划两级规划模型及其求解算法。依据项目的承继关系,将所有项目划分为若干子群,各子群内部的项目之间存在承继约束,子群之间仅有优先关系,进而获得了资源受限下资源配置平衡的两级规划模型。基于遗传算法的基本结构,引入免疫系统的多样性、记忆性等特征,获得了求解此模型的免疫遗传算法。数值实验结果表明了该模型设计的合理性及算法的有效性。 This work investigates a bi-level programming model of resource allocation balance subjected to multi-project selection planning with constrained resource and inheritance in project planning management. In this model, all given terms are divided into multiple subpopulations with only the relation of superiority between them, among which each subpopulation includes multiple terms with the relation of inheritance. Further, a new immune genetic algorithm is proposed based on the structure of the basic genetic algorithm in relation to the characteristics of memory and diversity in the immune system. Experimental results and comparison show the rationality of the model and the effectiveness of the algorithm proposed.
作者 雷宏 张著洪
出处 《计算机工程与设计》 CSCD 北大核心 2010年第9期1992-1994,2154,共4页 Computer Engineering and Design
基金 教育部科学技术研究重点基金项目(208125) 贵州大学研究生创新基金项目(校理工2009031)
关键词 多项目选择计划 资源平衡 拓扑排序 免疫遗传算法 网络计划图 multi-projectselection planning resource allocation topological sorting immune genetic algorithm network planning chart
  • 相关文献

参考文献9

二级参考文献26

共引文献128

同被引文献34

  • 1白思俊.资源有限的网络计划与启发式优化方法及其评价与选择——启发式优化方法综述[J].中国管理科学,1993,1(2):30-38. 被引量:36
  • 2袁晓辉,袁艳斌,王乘,张勇传.一种新型的自适应混沌遗传算法[J].电子学报,2006,34(4):708-712. 被引量:48
  • 3邓林义,林焰,金朝光,陈明.资源约束下多项目调度的拓扑优化方法[J].系统仿真学报,2007,19(16):3846-3849. 被引量:11
  • 4Hartmann S. A competitive genetic algorithm for resource-constrained project scheduling[ J]. Naval Research Logistics, 1998,45:733 - 750.
  • 5Boctor F F. Resource-constrained project scheduling by simulated annealing[ J ]. International Journal of Production Research, 1996,34: 2335 - 2351.
  • 6HEGAZY T. Optimization of resource allocation and leveling using genetic algorithms [ J]. Journal of Construction Engineering and Management, 1999, 125(3): 167-175.
  • 7KUMANAN S, JEGAN J G, RAJA K. Multi-project scheduling using an heuristic and a genetic algorithm[ J]. The International Journal of Advanced Manufacturing Technology, 2006, 31 (3) : 360 - 366.
  • 8GONCALVES J F, MENDES J J M, RESENDE M G C. A genetic algorithm for the resource constrained multi-project scheduling problem[ J]. European Journal of Operational Research, 2008, 189 (3): 1171-1190.
  • 9DOREEN K , ARMIN S . A heuristic solution framework for the constrained muhi-project scheduling problem with sequence-dependent transfer times [ J ]. European Journal of Operational Research, 2009, 197(2) : 492 - 508.
  • 10S? NKE HARTMANN. A self-adapting genetic algorithm for project scheduling under resource constraints[ J]. Naval Research Logistics, 2002, 49:433-488.

引证文献5

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部