摘要
以岚桥海景国际饭店筏板基础混凝土工程为例,介绍了大体积抗渗混凝土配合比设计,具体阐述了该工程冬期施工中大体积混凝土配合比的确定及其施工过程中的质量控制措施,实践证明该工程所用混凝土配合比达到并超过了设计要求,确保了混凝土质量。
Taken construction works of raft foundation of Lanqiao Haijinginternational Hotel as example the mix proportion design of the mass water-tight concrete is introduced.The determination of the mix proportion of mass concrete in winter construction as well as quality control measures adoptedin construction are elaboratedin detail.Practice showdesigned mix proportion can meet design requirements of engineering to ensure concrete quality.
出处
《山西建筑》
2010年第17期156-157,共2页
Shanxi Architecture
关键词
高性能混凝土
冬期施工
配合比
质量控制
抗渗性能
high-performance concrete
winter construction
mix proportion
quality control
seepage resistance