摘要 该文主要介绍对柬埔寨斯登沃代一级水电站工程消能方案试验研究情况,通过对原方案反复试验验证和修改后,提出的"宽尾墩+跌坎式消力池+水跃坎"联合消能工,很好地解决了工程的消能防冲难题,节省了工程量,已被工程设计采纳。 This text introduce the process of experimental staudy on hydraulic model in Cambodia stung atay first hydroelectric station,Through repetitive experimental rvision of original design,a better joint energy dissipater scheme of flaring gate pier and plunge pool and hydraulic jump bucket can solove the problem of energy dissipation and erosion control,this scheme economize the project amount and adopted by the station.
作者 杨亚斌
出处 《水科学与工程技术》 2010年第3期65-67,共3页 Water Sciences and Engineering Technology
关键词 宽尾墩 水工模型试验 联合消能工 flaring gate pier hydraulic model test joint energy dissipater
  • 相关文献

参考文献7

二级参考文献9

  • 1余挺,邓军,夏勇,贺昌林,许唯临.翻卷水舌鼻坎挑流的紊流数值模拟[J].水利水电技术,2005,36(5):37-39. 被引量:9
  • 2刘国贵,刘国华,陈斌.红石岩水电站工程动床模型试验研究[J].水力发电,2005,31(6):27-28. 被引量:5
  • 3徐木运.洞巴水电站整体水工模型试验研究报告[R].南宁:广两水电科学研究院,2004.
  • 4斯里斯基C.M.,<高水头水工建筑物的水力计算>[M],毛先民、杨立信,北京:水力电力出版社,1984,242-248.
  • 5夏勇,溪洛渡水利枢纽溢洪道挑坎体型研究报告[M],成都:四川大学水电学院高速水力学国家重点实验室,2000.4.
  • 6梁川、张先起,紫坪铺水利枢纽工程溢洪道单体水工模型试验报告[M],成都:四川大学水电学院高速水力学国家重点实验室,2001.2.
  • 7吴持恭.水力学[M].北京:高等教育出版社,1982..
  • 8钦荣著.河流推移质运动理论及其应用[M].北京:中国铁道出版社,1996..
  • 9张先起,付强,梁川.高陡槽溢洪道挑流鼻坎体形研究[J].东北水利水电,2002,20(2):7-9. 被引量:7