大采高综采工作面片帮加剧机理分析及防治措施 被引量:42

Analysis on Spalling Increased Mechanism of Fully Mechanized High Cutting Coal Mining Face and Prevention Measures
下载PDF
导出
摘要 片帮冒顶制约了大采高综采工作面安全高效开采,因此对大采高综采工作面片帮加剧机理进行分析,发现影响工作面片帮的因素有采高、内摩擦角等,运用数值模拟的方法研究了不同采高下的煤壁片帮条件及临界护帮长度,并结合神东矿区的煤层条件,提出提高支架前端的护帮力、支架初撑力和前端支顶力,增加护帮的长度等控制大采高综采工作面片帮的6种措施。 The spalling and roof falling had restricted the safety and high efficient coal mining of the fully mechanized high cutting coal mining face.Thus the spalling increased mechanism of the fully mechanized high cutting coal mining face was analyzed.The factors caused the coal face spalling would be mining height,inner frictional angle and others.The numerical simulation method was applied to the study the coal face wall spalling condition and the coal wall critical support length under the different mining height.In combination with the seam conditions in Shendong Mining Area,there were six measures to increase the coal wall support force at the front of the powered support,the powered support initial support force,the front support force,the length of the coal wall protection plate and other spalling control of the fully mechanized high cutting coal mining face.
出处 《煤炭科学技术》 CAS 北大核心 2010年第7期38-40,64,共4页 Coal Science and Technology
关键词 大采高综采 片帮冒顶 数值模拟 护帮长度 采高 防治措施 fully mechanized high cutting coal mining face spalling and roof falling numerical simulation coal wall protection length mining height prevention and control measures
  • 相关文献

参考文献7

二级参考文献14

共引文献314

同被引文献183

引证文献42

二级引证文献221

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部