摘要
文章结合龙江大桥3#墩基础施工实例,对桥墩高水位筑岛围堰的施工方法进行探讨,着重介绍了土石筑岛围堰、水下承台施工等桥墩基础施工技术。
Based on the actual construction practice of 3# Pier Foundation,the article dis-cusses the construction method to built island and cofferdam of the high water level bridge,and mainly introduces the construction technique of pier foundation,such as earth-rock cof-ferdaming and building island,underwater pile cap construction etc.
出处
《西部交通科技》
2010年第6期113-116,共4页
Western China Communications Science & Technology
关键词
桥涵工程
基础施工
技术
Bridge and culvert engineering
Foundation construction