变速风力发电机提供调频备用容量研究 被引量:26

Variable-speed wind turbines provide primary reserve for frequency control
下载PDF
导出
摘要 提出一种新的调频控制策略,它利用变速风力发电机快速功率控制能力主动提供一次调频备用容量。该策略通过风力发电机的卸载运行,即使在风速大范围变化,也能够确保一次调频备用容量。在低风速时风电机组作为飞轮(旋转备用)电机运行,利用存储在涡轮叶片的旋转能量提供短期有功电力支持;在中风速时根据卸负荷最佳功率提取曲线运行风力发电机,建立电力储备;在高风速时采用桨距控制或修改转速设定点保持在满负荷时合适的电力储备。仿真实验证明该策略能有效地控制备用容量,实现变速风力发电机对系统频率的控制。 A frequency control strategy is presented,which utilizes the fast response capability of VSWT to actively provide the primary reserve.It unloads the wind turbine to ensure the primary reserve for a large range of wind speed.At low wind speed,the wind turbine operates as a flywheel to utilize the kinetic energy stored in the rotational masses for the temp active power support.At middle wind speed,the wind turbine operates according to the unloading optimal energy conversion curve to set up the active power reserve.At high wind speed,the wind turbine operates with full load at the modified rotor speed set point or under the pitch control to keep an appropriate active power reserve.Simulative experiments indicate its effectiveness in the power reserve control for frequency control.
出处 《电力自动化设备》 EI CSCD 北大核心 2010年第8期75-80,共6页 Electric Power Automation Equipment
基金 上海市曙光计划资助项目(07SG11) 教育部新世纪人才资助项目(NCET-08-0356)~~
关键词 风能发电 变速风力发电机 卸载运行 频率控制 一次调频备用 wind power generation VSWT unloading operation frequency regulation primary reserve
  • 相关文献

参考文献10

  • 1TSILI M,PATSIOUAS C. Grid code requirements for large wind farms[EB/OL]. [2009-11 - 15 ]. http ://users.ntua.gr/stpapath / Paper_2.72.pdf.
  • 2SOLDER L. Reserve margin planning in a wind-hydro-thermal power system[J].IEEE Trans on Power Systems,1993,8(2): 564-571.
  • 3WOBBEN A. Method for operating a wind power station and wind power station:USA,Patent 6891281[P]. 2005-05-10.
  • 4MORRENTAL J. Wind turbines emulating inertia and supporting primary frequency control[J]. IEEE Trans on Power Systems, 21 (1) :433-434.
  • 5de ALMEIDA R G,LOPES J A P. Participation of doubly fed induction wind generators in system frequency regulation[J]. IEEE Trans on Power Systems, 2007,22 (3) : 944-950.
  • 6de ALMEIDA R G,CASTRONUOVO E D,LOPES J A P. Optimum generation control in wind parks when carrying out system operator requests[J]. IEEE Trans on Power Systems,2006,21 (2): 718-725.
  • 7EKANAYAKE J,JENKINS N. Comparison of the response of doubly fed and fixed-speed induction generator wind turbines to changes in network frequency[J].IEEE Trans on Energy Conversion, 2004,19 (4) : 800-802.
  • 8EKANAYAKE J,HOLDSWORTH L,JENKINS N. Control of DFIG wind turbines[J]. Power Engineering Journal,2003,17(1) :28-32.
  • 9MILLER N W,PRICE W W,SANCHEZ-GASCA J J. Dynamic modeling of GE 1.5 and 3.6 wind turbine-generators[R]. New York, USA :GE, 2003.
  • 10CHINCHILLA M,ARNALTES S,BURGOS J C. Control of permanent magnet generators applied to variable-speed wind-energy systems connected to the grid[J]. IEEE Trans on Energy Conversion, 2006,21 ( 1 ) : 130-135.

同被引文献371

引证文献26

二级引证文献525

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部