摘要 针对立井箕斗定重装载系统闸门关闭所需提前量难以设定,从而导致实际装载质量与系统设定值不一致的问题,利用Simulink软件对立井箕斗定重装载过程进行了建模与仿真,并对不同装载速度下闸门关闭所需的提前量进行了计算,有利于提高系统的装载精度,满足定重装载要求。 In view of the problems, such as the skip weight-fixed loading system in vertical shaft is difficult to set the strobe closing amount in advance, the actual load weigh is different with the system setting, take use of simulink software build model and simulate the system, calculated the strobe closing amount of advance in different loading speeds, help to improve the accuracy of the loading system to meet the requirement of weight-fixed loading.
出处 《煤矿机械》 北大核心 2010年第9期16-18,共3页 Coal Mine Machinery
基金 陕西省教育厅专项基金(09JK574)
关键词 立井箕斗定重装载系统 提前量 仿真 SIMULINK skip weight-fixed loading system in vertical shaft amount in advance Simulation Simulink
  • 相关文献

参考文献3

二级参考文献10

共引文献14

同被引文献2

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部