从开发方的角度,在系统总结水电行业现有风险研究成果的基础上,重点考虑了援外工程的特殊性,运用故障树方法,对国际BOT水电项目的风险控制问题进行了探讨,进一步完善了国际BOT水电项目的风险管理研究。
This paper,from the view point of the development party,gives key consideration to the particularities of foreign project based on the available risk analysis results in the hydropower industry,and by the fault tree method discusses the risk control of international BOT hydropower project and improves the risk management study further.
出处
《西北水电》
2010年第4期95-102,共8页
Northwest Hydropower
关键词
BOT
水电项目
风险管理
故障树
BOT
hydropower project
risk management
fault tree