基于主成分分析和目标规划法的高速公路施工进度目标规划模型 被引量:4

Goal Programming Model for Highway Construction Schedule Based on the Principal Component Analysis and Goal Programming
下载PDF
导出
摘要 针对当前施工进度管理方法相对简单等问题,基于风险识别的理论,从硬指标和软指标两个角度设计高速公路项目施工进度指标体系;充分利用主成分分析法和目标规划法在数据处理上的优势,建立高速公路项目施工进度目标规划模型;通过实例分析加以验证.该模型为解决施工进度目标规划数据庞大复杂、不系统等难题给出一条具有可操作性的路径. In view of relative simplicity of the current method for construction schedule management,this based on the risk identification theory paper mainly designs a highway project construction schedule index system from the two aspects-strong index and soft index.Making full use of the superiority of the principal component analysis and programming in data processing,this paper establishes a high-way construction projects schedule programming model,which is testified by analyzing a realistic example.The model addresses a feasible and workable path for solving the difficulties that the data are complex and not systemic in the goal programming.
出处 《武汉理工大学学报(交通科学与工程版)》 2010年第4期788-792,共5页 Journal of Wuhan University of Technology(Transportation Science & Engineering)
基金 国家自然科学基金项目资助(批准号:70772058)
关键词 主成分分析法 目标规划法 风险识别 施工进度 指标体系 评价模型 the principal component analysis goal programming risk Identification construction progress index system evaluation model
  • 相关文献

参考文献7

二级参考文献33

共引文献48

同被引文献28

引证文献4

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部