利用电渗法降低过湿土的含水量是目前路基填筑的一项新技术。通过室内试验得出的不同电流密度下排水量与时间的关系及各层含水量的变化规律,为电渗技术在路基中的广泛应用奠定了基础。
It is a new technique that using electro-osmosis method to lower water ratio of overwet soil used as subgrade filler.Through indoor tests,the relationship between the water discharge and time as well as the law of each layer's water content under varied current density are obtained,which provide a basis for improving the extended application of electro-osmosis technology in subgrade constuction.
出处
《交通标准化》
2010年第21期77-80,共4页
Communications Standardization
关键词
过湿土
电渗
含水率
over-wet soil
electro-osmosis