结合泰州大桥中塔钢塔柱吊装施工实践,介绍了世界最高的纵向人字形、横向门式框架钢塔柱吊装施工工艺和监控方法。监测结果显示,施工满足设计和验收标准要求。
Combining the hoisting construction practice of steel pillar in the middle pillar of Taizhou bridge,this paper introduces the hoisting construction technology of steel pillar,which is the world's highest transverse and longitudinal herringbone portal frame,and also introduces its monitoring method.It meets the design and the acceptance standard requirements after construction by monitoring.
出处
《中国港湾建设》
北大核心
2011年第2期51-54,共4页
China Harbour Engineering
关键词
钢塔柱
吊装施工工艺
施工监控
steel pillar
hoisting construction craft
construction supervision