盾构在砂层中的施工技术探讨 被引量:3

A Study on Construction Technology of Tunnel Shield in Sand Stratum
下载PDF
导出
摘要 盾构隧道在砂层施工时,由于砂性土摩擦角较大,渣土流动性差,排土困难,容易发生喷涌,造成地面沉降,影响周边建筑物、管线与道路安全。本文以郑州市轨道交通1号线博学路站~体育中心站区间隧道盾构施工为例,认为砂层施工中必须合理设定土压、改良渣土、严控出土量、防止螺旋输送机喷涌、盾尾密封与注浆工作,才能确保盾构在砂层中的平稳、高效掘进。 In shield tunnel construction,due to large friction angle of sandy soil,poor liquidity of muck and dumping difficulties,the tunnel shield passing through the sand stratum maybe result in inrushing,which bring about the land subsidence and jeopardize the nearby building,pipeline and road.In this paper,the tunnel shield construction of Zhengzhou rail transit line1 between Boxue Station and Tiyuzhongxin Station is taken as an example.It's deemed that it must set a reasonable soil pressure,improve muck,strict control the amount of muck,prevent screw conveyor spewing,seal shield tail and grout during sand stratum construction,so that a stable and efficient excavating work done by tunnel shield in sand stratum can be ensured.
出处 《铜业工程》 CAS 2011年第4期83-85,16,共4页 Copper Engineering
关键词 土压平衡盾构 砂土层 隧道掘进 控制技术 EPB Shield sand stratum tunnel excavating construction technology
  • 相关文献

参考文献4

二级参考文献10

共引文献62

同被引文献10

引证文献3

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部