摘要
柏叶口水库坝底地处文峪河谷河段,地形条件复杂,河谷高差较大。文中论述了该水库坝址测量控制网布设的原则和具体方法。通过采用"折叠线形锁"控制网的办法解决了施测过程中的困难,取得了很好的效果。
The dam site of Baiyekou Reservoir is located in a narrow gorge of Wenyu River reach.Its topography condition is complex and the elevation difference of river valley is obvious.In this paper,the layout principle of control network to survey topography of this dam site and concrete survey method are introduced.By means of the folded linear triangulation chains network methed,the difficult problems that are encountered is survey process are solved,and the good effect is obtained.
出处
《山西水利科技》
2011年第3期26-27,共2页
Shanxi Hydrotechnics
关键词
测量
控制网布设“
折叠”线形锁
survey
layout of control network
folded linear triangulation chains