高地下水位土方开挖降水施工 被引量:3

Dewatering Construction in the Excavation at a High Water Table
下载PDF
导出
摘要 李河渠道倒虹吸开挖深度大,约20 m,低于地下水位17 m.倒虹吸开挖必须在相对干燥的环境中进行,故采用管井法将地下水位降至开挖面以下或截断地下水,避免施工时发生管涌或流土破坏地基.经抽水试验,应用管井法降水保证了基坑基本在干燥情况下施工,为相似地区的降水施工提供了借鉴. The excavation depth in the inverted siphon project of Lihe River is large and up to 20 m which is 17 m deeper than the water table.However,the inverted siphon excavation must be made in a relatively dry environment.In order to avoid destroying the foundation due to piping or quick soil in the construction,the tube-well method was used to dewater and make the water table down to the excavation face or cut off the groundwater.By the means of a pumping test,it manifested that application of the tube-well method had ensured the pit to be constructed under dry conditions.It would provide a reference for the dewatering construction in similar areas.
作者 杨卫 丛苹
出处 《华北水利水电学院学报》 2011年第5期122-124,共3页 North China Institute of Water Conservancy and Hydroelectric Power
关键词 高地下水位 管井法 降水 措施 high water table tube-well method dewatering measures
  • 相关文献

参考文献3

  • 1河南省水利勘测有限公司.初步设计阶段岩土工程地质勘测报告[R].郑州:河南省水利勘测有限公司,2005.
  • 2建设部综合勘察研究设计院.JGJ/T111-98建筑与市政降水工程技术规范[s].北京:中国建筑工业出版社,1999.
  • 3中国水利水电第七工程局南水北调焦作I段Ⅲ标项目部.李河倒虹吸施工降水观测资料[R].焦作:中国水利水电第七工程局南水北调焦作I段Ⅲ标项目部,2010.

共引文献2

同被引文献14

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部