摘要
在复杂地质条件下,高填方施工难度大,主要研究了原地表不良地质条件的整治、滑坡体的处理和施工质量控制与监测技术等,通过工程实践。
At the condition of the complex engineering geology,it is very difficult for high-filling construction.In this paper the authors introduced handling methods of harmful geology condition,treatment of slipping soil mass,controlling for condition quality and observation technology.Remarkable effects have been gained trough engineering practice.
出处
《西部探矿工程》
CAS
1999年第S1期55-57,共3页
West-China Exploration Engineering
关键词
工程地质
高填方
滑坡土体
监测技术
施工
engineering geology,high-filling,slipping soil mass.observation technology