摘要
通过池州电厂预制桩现场试验,介绍了在打设塑料排水板后,饱和软黏土中打桩引起的土体超静孔隙水压力分布及消散规律,分析了影响土体超静孔隙水压力分布和消散的影响因素。试验结果表明,饱和软黏土中预制桩施工桩距宜大于3 m,时间间隔为6~8 h,预制桩施工的控制参数为超静孔隙水压力与上覆土体有效自重之比不大于1。
Based on an engineering case of the construction of prefabricated piles for Chizhou Power Plant,the distribution and dissipation laws of excess static pore water pressures induced by pile driving(prefabricated square piles) in the saturated soft clay with driven plastic drainage plates are introduced.The factors influencing the distribution and dissipation of the excess static pore water pressures in soils are analyzed.The test results show that the spacing of prefabricated piles in the saturated soft clay during their construction should be larger than 3 m;and the time interval should be 6-8 h.The control parameter for the construction of prefabricated piles is that the ratio of excess static pore water pressure to effective weight of superimposed soil should not be larger than 1.
出处
《岩土力学》
EI
CAS
CSCD
北大核心
2011年第12期3733-3737,共5页
Rock and Soil Mechanics
关键词
塑料排水板
预制桩
超静孔隙水压力
消散
plastic drainage plate
prefabricated pile
excess static pore water pressure
dissipation