摘要
结合宁杭客运专线徐舍特大桥跨钟张运河连续梁415号,416号主墩钢板桩围堰施工,详细介绍了水中钢板桩围堰设计、围囹安装、钢板桩打设、堵漏、挖泥、封堵等关键施工技术,为今后同类项目工程提供了宝贵经验。
Combining with steel sheet piling cofferdam construction of main pier 415# and 416# of continuous beam of large-span Zhongzhang cannel on Ning-Hang passenger special line,this article introduces some critical construction techniques including steel sheet piling cofferdam design,waling installation,steel sheet piling,penetration resistance,mud excavation,and sealing and so on,which has provided valuable experience for similar project engineering in future.
出处
《山西建筑》
2012年第8期86-88,共3页
Shanxi Architecture
关键词
水中墩
深基坑
钢板桩围堰
施工工艺
water pier
deep foundation pit
steel sheet piling cofferdam
construction technology