结合某桥闸高大立墙的施工实践,介绍了模板体系的使用材料、设计要点,详细阐述了脚手架与模板的拆除、安装工艺,以及成品、半成品的保护措施,对同类工程施工具有指导意义。
Combining with the construction practice of a bridge big vertical wall,this paper introduced the used materials,design key points of template system,elaborated in detail the removal,installation process of scaffold and formwork,and the protection measures of finished products,semi-finished products,had guiding significance for the similar engineering construction.