施工现场库存管理系统动力学仿真分析——以上海世博会某场馆为例 被引量:2

Analysis of Dynamics Simulation of Inventory Management System in Construction Site——Take a Pavilion in Shanghai Expo 2010 as an Example
下载PDF
导出
摘要 不同于制造业库存管理,建设项目的物料库存受施工现场的限制,既要求不能一次订购超出现场库存能力的数量,又要求建材供应不能出现间歇。为满足施工现场库存管理这一要求,文章采用系统动力学仿真的方法,从施工承包商的视角,以钢材为例,构建了施工现场钢材库存模型。通过模型对不同采购预警值进行了对比分析,得出了合理的预警值。并对支付延迟可能产生的影响,给出了相应的应对策略,保证了施工的正常进行。最后,将模型在中国2010年上海世博会某场馆工程建设中进行了检验。 Unlike the inventory management of manufacturing,the materials inventory of construction projects are limited by the construction site that the material’s order cannot be out of the inventory capacity and neither the supply can be intermittent.To meet the requirement of inventory management in the construction site,this paper adopts the system dynamics simulation method,takes the steel as an example,constructs an steel inventory model in construction site from the perspective of the construction contractor.The paper also obtains the reasonable value according to the comparative analysis of different procurement of early warning value in the model and puts forward to the corresponding coping strategies to ensure the normal construction.Finally,the paper takes a pavilion in Shanghai Expo 2010 as an example to verify the feasibility of the model.
出处 《华东经济管理》 CSSCI 2012年第7期124-127,共4页 East China Economic Management
基金 国家自然科学基金项目(70972071) 上海市科技委员会--世博科技专项项目(08dz0580700)
关键词 施工 库存 系统动力学 仿真 世博会 construction inventory system dynamics simulation Expo
  • 相关文献

参考文献9

二级参考文献37

共引文献90

同被引文献25

  • 1宁晓倩,王其藩.运用系统动力学模型进行项目时间/成本估算[J].科技导报,2004,22(9):54-57. 被引量:9
  • 2罗辉道,项保华.资源概念与分类研究[J].科研管理,2005,26(4):99-104. 被引量:32
  • 3Vaziri K,Carr P,Nozick L. Project planning for con-struction under uncertainty with limited resources [J],Journal of Construction Engineering and Management,2007,133(4): 268-276.
  • 4Afshar-Nadjafi B, Majlesi M. Resource constrained pro-ject scheduling problem with setup times after preemp-tive processes[J], Computers &- Chemical Engineering,2014,69: 16-25.
  • 5Browning T, Yassine A. Resource-constrained multi-project scheduling: Priority rule performance revisited[J]. International Journal of Production Economics,2010,126(2):212-228.
  • 6Lim A, Ma Hong, Rodrigues B,et al. New conceptsfor activity float in resource-constrained project manage-ment[J]. Computers Operations Research,2011,38(6): 917-930.
  • 7Cheng Minyuan,Tran D H, Wu Yuwei. Using a fuzzyclustering chaotic-based differential evolution with serialmethod to solve resource-constrained project schedulingproblems[J]. Automation in Construction, 2014,37 :88-97.
  • 8Azaron A,Katagiri H, Sakawa M. Time-cost trade-offvia optimal control theory in Markov PERT networks[J]. Annals of Operations Research, 2007,150(1) : 47-64.
  • 9Xu Jiuping, Zheng Huan,Zeng Ziqiang,et al. Discretetime-cost-environment trade-off problem for large-scaleconstruction systems with multiple modes under fuzzyuncertainty and its application to J inping-II Hydroelec-tric Project[J]. International Journal of Project Manage-ment, 2012,30(8): 950 - 966.
  • 10Tavana M, Abtahi A R, Khalili-Damghani K. A newmulti-objective multi-mode model for solving preemp-tive time - cost - quality trade-off project schedulingproblems [J], Expert Systems with Applications,2014,41(4): 1830-1846.

引证文献2

二级引证文献33

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部