摘要
根据深基坑工程的施工特点,提出了考虑分步开挖影响的带支护结构的计算方法.讨论了水平支撑体系的等效刚度、内支撑与围护墙的变形协调等问题.工程实例表明,在支护结构计算中考虑分步开挖的影响后,内力与变形计算结果与实测值较接近.
The multi-braced retaining structure has been widely applied to deep excavation engineering in soft clay. A calculation method for retaining structure considering the effects of steped excavation is presented, according to the construction characteristics of deep excavation engineering. Some problems are discussed, such as the mechanical mode and equivalent stiffness of horizontal bracing system, the deformation compatibility between the bracing and retaining wall. Finally, two excavation cases are given, which indicate that the effects of steped excavation can not be neglected in the calculation of the structure.
出处
《建筑结构》
CSCD
北大核心
2000年第5期36-39,共4页
Building Structure
关键词
深基坑
支护结构
围护墙
水平支撑
受力计算
deep pit
retaining structure
steped excavation
horizontal bracing