摘要
介绍了地铁车站的一种新型暗挖施工工法——拱盖法。拱盖法是在明挖法、盖挖法和PBA(洞桩法)工法基础上创建的适用于特殊地层的一种暗挖施工方法。该方法针对大连地区特殊地质条件,较好地适应了上软下硬采用钻爆法暗挖施工的大跨度地铁车站的施工要求,具有环境影响小、工序少、效率高、施工安全可靠等突出优点,并成功地应用于工程实践,取得了良好的经济效益和社会效益。
A new sub- surface excavation construction method for metro station, namely the arch - cover method is introduced, which is developed on the basis of cut - and- cover method, coverexcavation method and PBA construction method. This new method is applicable for special strata and could meet the construction requirements of metro station, especially the large span of metro station on homogeneous or non - homogeneous soils, and often uses the drilling- and- blasting method. The merits of this method include less influence on environment, simpler working procedure, higher efficiency and safety. It has been successfully used and brought about remarkable economic and social benefits.
出处
《城市轨道交通研究》
北大核心
2012年第8期145-148,共4页
Urban Mass Transit
关键词
地铁车站
暗挖施工
拱盖法
metro station
sub - surface excavation construction
arch - cover method