北京财富中心二期写字楼全焊接钢板墙施工工艺 被引量:4

CONSTRUCTION PROCESS OF ALL-WELDED STEEL PLATE WALL OF OFFICE BUILDING IN BEIJING FORTUNE PLAZA PHASE Ⅱ
下载PDF
导出
摘要 北京财富中心二期写字楼-4~20层核心筒墙体中间为整体全熔透焊接钢板墙.焊缝集中和大量热输入导致钢板墙焊接过程产生了较大的应力及焊接变形,施工中采取了分段跳焊、对称焊接、严格控制焊接顺序、设置变形控制工艺梁、预留焊接收缩量等工艺,制作了可重复使用的焊接挂架,基本解决了焊接变形过大的问题。 In Beijing Fortune Plaza Phase II office building project, the core-tube wall on -4 to 20 floors is all-welded steel wall. Concentration of welds and huge heat input cause relatively big stress and obvious welding deformations during welding of the steel plate wall. Therefore, skip block welding, symmetry welding, strict control of welding sequence, setting of deformation control beam and reservation of welding shrinkage allowance are adopted during the construction and reusable welding manipulator is fabricated to basically avoid excessive welding deformation during construction.
出处 《建筑技术》 2012年第10期877-880,共4页 Architecture Technology
关键词 全焊接钢板墙 焊接变形控制 焊接操作架 all-welded steel plate wall welding deformation control welding manipulator
  • 相关文献

参考文献2

二级参考文献7

  • 1张斌,寇朝显.典型箱形梁特厚板焊接变形控制[J].焊接,2006(8):53-55. 被引量:6
  • 2GB50017-2003.钢结构设计规范[S].[S].,..
  • 3JGJ81-2002.建筑钢结构焊接技术规程[s].[S].,..
  • 4JGJ102-2003.玻璃幕墙工程技术规范[S].[S].,2003..
  • 5JGJ99-1998.高层民用建筑钢结构技术规程.[S].,..
  • 6JGJ 133-2001,金属与石材幕墙工程技术规范[S].
  • 7铝合金结构设计规范.GB50429-2007[S].2007.

共引文献10

同被引文献25

引证文献4

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部